|

In most cases the purchase price of equipment includes
initial commissioning of the equipment on site. Commissioning
should not be confused with installation which must be arranged
separately. The following notes explain what the commissioning
comprises and what the commissioning engineer will expect
to find when attending site.
If the equipment purchased is approved for the re-sale of
fuel then a Weights & Measures appointment will be booked
on your behalf timed to tie in with the visit of the commissioning
engineer. If a Weights & Measures stamp is not required,
then you should inform us immediately as a charge is made
for a cancelled booking. Local authority fees are not payable
by Pumptronics.
Commissioning of the equipment will be undertaken on behalf
of Pumptronics by a trained third-party company operating
locally to the site. The commissioning company will contact
you prior to delivery to organise a suitable commissioning
date and time with you.
The following works must be undertaken
prior to commissioning:
- The pump should be securely bolted down to an island of
minimum 150mm height as per the relevant installation drawing.
- The pipework should be connected into the pump as per
the installation drawing.
- The mains cable with a minimum of 1.5m of free cable should
be available at the pump, together with the same length
of data cable if the unit is to be connected to third party
equipment. The commissioning engineer will make the connections
within the pump. Under no circumstances should these connections
be made by unauthorised personnel as this will invalidate
the guarantee on the equipment.
Fuel and mains power must be available prior to commissioning.
The complete installation should
be in accordance with national and local regulations eg:
- European Standard EN13617:2004
- Health & Safety Guidelines
- IEE Regulations
Prior to commissioning the equipment,
the commissioning engineer will check that:
- The pump is level and bolted securely to an island of
minimum height 150mm with the securing bolts not obscured.
- The pump is situated such that the switches and key positions
can be accessed and the panels removed for future maintenance.
- The pipework connections are to the correct height and
location and positioned to avoid all moving parts (belts/pulleys).
- The base sealing cap is fitted and sealed (where applicable)
and that all electrical wires and connections pass through
the sealing cap and are positioned to avoid moving parts
(belts/pulleys).
- The earth connections are properly made, both to the cable
casing/armour and an independent earth conductor, and that
all equipment is effectively bonded with no earth loops
via comms cables.
- Any peripheral equipment to which the pump is to be connected
is earthed/bonded down properly.
If the commissioning engineer is not satisfied with any of
these points then you will be advised. If the deficiency is
minor, the engineer will normally continue with the commissioning
and will ask that the deficiency be rectified, ideally prior
to completion of his visit. Any deficiencies still present
on completion of the commissioning will be noted on the customer
satisfaction form which you will be asked to sign. If the
deficiency is more major then engineer will explain what is
required and discuss with you whether it is more appropriate
for the engineer to remain on site whilst the problem is rectified
or to make a return visit. In either case we regret that the
additional time incurred or the re-visit will be chargeable.
It is expected that the equipment is available and ready
for commissioning at the time agreed. If an engineer is unacceptably
delayed waiting to start commissioning then we reserve the
right to charge for the additional engineers time.
We trust that these notes are of assistance when preparing
for your commissioning visit.
|